10 September 2023

Power line removed

Zdjęcie przed i po. Działki w Machowinku.

We are proud to announce that we have successfully completed the cabling of the medium voltage overhead power line. Work on this task began almost at the beginning of our investment.

First, a contract with the operator. Then a tedious stage of arrangements and design. Finally, execution. And is :).

Thanks to this, it is definitely safer and even more beautiful. We invite you for a walk around the Ustoria plots.

Other news

Zakończone prace związana z budową sieci

Completion of the Power Network Construction in Ustoria

6 October 2025
The construction of the power network in Ustoria has come to an end. Cable connection boxes have been installed next to the plots with signed connection agreements, and the network has been extended across the entire area. From now on, connecting any additional plot is just a simple formality. Continue reading
Rozpoczęcie prac budowlanych - sieć elektro

Commencement of Electrical Infrastructure Construction at Ustoria

8 July 2025
New Development Phase for the Baltic Sea Project The Ustoria project has entered its next implementation phase. ENERGA company has commenced work on the construction of electrical grid infrastructure, which will provide complete utilities for all offered plots. Infrastructure Development Progress Intensive installation works are currently being carried out on the investment site, including: Comprehensive […] Continue reading
Nazwy ulic w Ustoria

🗓️ New Street Names in Ustoria

28 March 2025
Ustka Municipal Council adopted Resolution No. XII.143.2025 on March 8, 2025, which officially assigns names to the streets located within the Ustoria development Continue reading